A Brief Overview

January 2012
25/01
Tenders close for station


March 2012
10/03
Lyndoch Station demolished


April 2012
03/04

Partek HomepageContractor - PARTEK - visits site for final discussions with Brigade representatives
Projected start date - 16/04 with a 21 week build period

18/04

Building work starts - contractors on-site
Demolishing of old slab - leveling and preparation of site begins

27/04
Site fenced off - Building site levelled off, site compacted and ready for next stage


May 2012
18/05
Mesh and plumbing being carried out prior to slab being poured
25/05
Concrete poured for administration area


June 2012
08/06
Framework for office area complete


July 2012
10/07
Shed framework to go up this week subject to weather
Building date extended towards end of September due to weather and shed delay
17/07
Framework for shed commenced
25/07
Side wall and roof frame structure up
31/07
Appliance Bay - all wall, roof and main roof panels up


August 2012
03/08
Plumbing, Electrical and Data cabling - being run
Expected that concrete for shed to be poured next week
31/08
Close to lockup stage now - main doors on, internal wall lining completed - close to 2nd stage fix.Rendering of external walls on administration area commenced.
Still awaiting concrete floor in appliance bay - should be next week


September 2012
21/09
Expected Stage 1 handover date - this consists of the main building
This is being undertaken so that the landscaping and remainin external works can be undertaken - may be delayed by a week. New date now 12/10
27/09 Work on the lighting and wiring to the Applaince Bay, installation of the air-conditioning
28/09 Gawler Custom Cabinets install desk and kitchen. External painting of the administration area wall.


October 2012
17/10
Finishing off - inside & out - screens around aircondiftioner, final fixtures on doors etc. General clean up
19/10 Pre-handover Inspection by PARTEK
26/10 Stage 1 Handover
27/10 Moving Day - all hands on deck to move equipment from back store shed to station


November 2012
02/11
Stage 2 Start
Fence lines being demolised to make way for good neighbourly fencing
   

 

Photos

Click on a picture below to see a larger version

     

 

Additional Information