| January 2012 |
25/01 |
Tenders close for station |
|
|
|
| March 2012 |
10/03 |
Lyndoch Station demolished |
|
|
|
| April 2012 |
03/04 |
Contractor - PARTEK - visits site for final discussions with Brigade representatives
Projected start date - 16/04 with a 21 week build period |
18/04 |
Building work starts - contractors on-site
Demolishing of old slab - leveling and preparation of site begins
|
27/04 |
Site fenced off - Building site levelled off, site compacted and ready for next stage |
|
|
|
| May 2012 |
18/05 |
Mesh and plumbing being carried out prior to slab being poured |
25/05 |
Concrete poured for administration area |
|
|
|
| June 2012 |
08/06 |
Framework for office area complete |
|
|
|
| July 2012 |
10/07 |
Shed framework to go up this week subject to weather
Building date extended towards end of September due to weather and shed delay |
17/07 |
Framework for shed commenced |
25/07 |
Side wall and roof frame structure up |
31/07 |
Appliance Bay - all wall, roof and main roof panels up |
|
|
|
| August 2012 |
03/08 |
Plumbing, Electrical and Data cabling - being run
Expected that concrete for shed to be poured next week |
31/08 |
Close to lockup stage now - main doors on, internal wall lining completed - close to 2nd stage fix.Rendering of external walls on administration area commenced.
Still awaiting concrete floor in appliance bay - should be next week |
|
|
|
| September 2012 |
21/09 |
Expected Stage 1 handover date - this consists of the main building
This is being undertaken so that the landscaping and remainin external works can be undertaken - may be delayed by a week. New date now 12/10 |
| 27/09 |
Work on the lighting and wiring to the Applaince Bay, installation of the air-conditioning |
| 28/09 |
Gawler Custom Cabinets install desk and kitchen. External painting of the administration area wall. |
|
|
|
| October 2012 |
17/10 |
Finishing off - inside & out - screens around aircondiftioner, final fixtures on doors etc. General clean up |
| 19/10 |
Pre-handover Inspection by PARTEK |
| 26/10 |
Stage 1 Handover |
| 27/10 |
Moving Day - all hands on deck to move equipment from back store shed to station |
|
|
|
| November 2012 |
02/11 |
Stage 2 Start
Fence lines being demolised to make way for good neighbourly fencing |
| |
|
|